WSTCF management process

From the EM RE(S) Autumn Working Guidance 2026 v1.1 — report → FMS / MYIM → classification → response → sign-back, with the Appendix C scenarios and Appendix D sign-back levels.

Process flow

  1. 1 — Report received
    WSTCF reported by a signaller (train on TC showing clear) or by an RCM alarm (RADAR / Centrix). Log time, TC, line and reporting train.
  2. 2 — FMS fault raised
    Raise the failure on FMS and record all relevant information in MYIM — a separate MYIM file per track circuit, linked together (2026 guidance §9). Record on the daily CCIL 'Autumn Suspect WSTCF' log (created 00:01 for 24h); confirmed failures transfer to the per-DU WSTCF CCIL Master Log, open all season.
  3. 3 — Classify
    Classify High / Low / Negligible using the hazard index (NR/L3/SIG/10047 Mod 03 §10.1) and the Appendix A flow chart (NR/L3/SIG/11231 Part 05 Module S04). RCM trace evidence drives classification — a blip under 300ms is Negligible, a sub-1 s boundary transition with the abutting TC occupied is not a WSF; no RCM at site means treat as High.
  4. 4 — Operational response
    Apply the Appendix C scenario response: Reg 3.5 / double block / TS11 as required, liaising with the Level 3 SFI so special working prevents a recurrence; arrange a wheelset check of the train involved within 30 minutes of the SCWO. Ops Managers keep the live special working register up to date.
  5. 5 — Treatment before attendance
    Where RCM is fitted and traces indicate railhead contamination there is no immediate requirement to send MOM / S&T to site, nor to wait for them before the railhead is treated by RHTT / MPV — but the Level 3 SFI must give permission before treatment starts. The L2/L3 SFI may still call staff to site where there is doubt or treatment is not effective.
  6. 6 — Sign back
    Sign back at the Appendix D level for the classification (FF/NFF). The L2/L3 SFI can sign a TC back using RCM information exclusively and advise the Operations Manager to instruct the signaller to remove special working. L2/L3 closure needs the SFI report/statement, II RCM traces and an interlocking logger / technician's terminal extract.
  7. 7 — Report to NOC
    High-risk failures: Form A (first failure) / Form B (simplified, subsequent on same circuit) to the NOC by 18:00, otherwise by close of play. TS11 s15 / F3.17A form daily.
  8. 8 — Restore normal working
    Remove special working per the restoration rules below (RHTT pass / 3 consecutive trains + good RCM traces), reinstating on red/black forecasts.
  9. 9 — Withdraw special working
    Formal withdrawal with photographic evidence and the Withdrawal form to the NOC (see withdrawal procedure below).

Scenario guidance (Appendix C)

RefSituationActionsSign-back
1.1Signaller reports a TC blip under a train (RCM fitted)Ops: alert Control of a potential High-risk TC (treated as High until evidence disproves it), apply Reg 3.5 working, create the MYIM report. TSE / IIT: check the TC boundary transition and SCWO timing on RADAR & Centrix; risk is determined at this point (SMTH Part 05 Module S04). (A) Proved High or Low: inform the incident controller, ask for wheelsets to be checked (within 30 min), escalate to SFI Level 2. (B) Negligible with improved traces confirmed by TSE / IIT: Control decides when to remove the special working.High/Low: full sign-back per the TC table, L2 or L1 (App D). Negligible: Control, after discussion with L1 (or L2 in certain scenarios), may remove the working without further escalation.
1.2Signaller report, no RCM fittedTreat as High risk and escalate to SFI Level 1 or 2 for interlocking checks (section 4 of the guidance). Confirm RCM is genuinely not fitted.Full sign-back required.
1.3Driver reports a change of aspect (COA) on an approach-release signalAs 1.1: alert Control (High until disproved), apply Reg 3.5, create MYIM. TSE / IIT check the boundary transition and SCWO timing; (A) High/Low — wheelset check within 30 min and escalate to SFI Level 2; (B) Negligible — Control decides when to remove the working.High/Low: full sign-back per the TC table, L2 or L1. Negligible: Control with L1 (or L2) may remove the working.
1.4RCM alarm (SCWO) — blip on a single track circuitFollow the Appendix A flow chart / SMTH Part 05 Module S04. TSE / IIT: (A) is the trace more or less than 300 ms? (B) apply the track-section boundary clause (§14); (C) escalate to SFI Level 1 / 2 / 3 according to the hazard level.High/Low: full sign-back per the TC table, L2 or L1. Negligible: if Reg 3.5 was implemented, remove after 2 recent good traces confirmed with L1 and/or L2.
1.5Late-reported RCM alarm — less than 8 hours agoTSE / IIT check the latest 2 train traces; if there has been a white period, run Reg 3.5 for the next 2 trains and confirm both traces are normal before removing. Under 8 hours: follow the Appendix A flow chart.High/Low: full sign-back per the TC table. Negligible: remove after 2 good traces with L1 and/or L2; if Reg 3.5 was never implemented there is no sign-back requirement.
1.6Late-reported RCM alarm — 8 or more hours agoWith continuous train occupation since and traces normal for 2 occupations, record as Negligible and close (beware differing train characteristics — a light engine may fail where heavier trains behave). If traces are not normal, treat as a live RCM failure under scenario 1.4.Special working not implemented — nothing to remove.
1.7Wheelset checksA request to check wheelsets must be made within 30 minutes of the SCWO. After that there is no need — any contamination has likely been removed.n/a
1.8First train of the dayCovered by operational procedures (first-train arrangements), not the WSTCF flow.n/a
1.9Overlay AHB track circuit (section 12 list)Reg 3.5 / special working is not required; treatment suggested at the nearest convenience. Check via a data logger (e.g. Centrix) whether the crossing entered a failed state.No special working implemented, so no removal requirement.
1.10Rail contamination from rustFollow Rule Book module TS11 (GERT8000-TS11 Issue 6, Dec 2023) — failure of, or work on, signalling equipment. Appendix E rusty-rail areas: Newstead loop, Wetmore, Cricklewood, Nadins GF, Leicester P4, Uttoxeter Loop, Leicester North Jct.n/a — TS11 arrangements
1.11TC SCWO where already protected by special workingNo change to the special working; when removal becomes desirable follow the normal procedure. Negligible-risk fault as the TC is already under Reg 3.5 — a fault must still be created and closed (vital for monitoring).Normal removal procedure when desired.

Sign-back levels (Appendix D)

FailureFault foundNo fault found
High — signal / interlocking / level-crossing failureL3L3
High — railhead contamination, unprotectedL2L3
Low — indication-only circuitL2L2
Low — RCM blip under 300msL1L2
Negligible — sequencing controls effectiveL1L2
Negligible — special block in forceL1L1

Where SFI Level 2 or 3 sign-back is required, closure needs (A) the SFI L2/L3 report or statement, (B) II RCM traces and (C) an extract from the interlocking loggers or technician's terminal. Sign-back at Level 2/3 may be granted on RCM evidence without site attendance. Where an event is considered NOT a wrong-side failure, the RCM traces are appended to the MYIM record (NR/SMTH Part 05 Module S04 §3.13).

Restoration of normal working

  • Remove Reg 3.5 after an RHTT pass — reinstate at the end of the day.
  • Remove special working after 3 consecutive trains operate the TC correctly with good RCM traces.
  • Re-implement Reg 3.5 when a red or black adhesion forecast is issued.
  • Where RCM is installed, removal may be considered once the contamination that caused the failure has been found and treated — RCM / Centrix evidence attached to the MYIM record and the S&TME satisfied the TCs are operating correctly.
  • Sites without RCM: at the end of the leaf-fall season the S&TME (or representative) and an Ops representative jointly inspect the railhead; the whole area must be free of contamination (allowing for leaves still on trees). A MOM photo to Control supports the decision; the fault is closed in MYIM when all parties agree.

Withdrawal of special working

  • Photographs of the railhead from 2–3 points plus a line-of-view shot.
  • Evidence sent to the Route Control Manager and DU S&T for agreement.
  • Withdrawal form submitted to the NOC.
  • Change circulated via the daily record of special working (Appendix K) and the 18:00 Autumn Log.

Grouping of TC failures

  • Failures may be grouped under one SFI pack when they share the same line, the same interlocking area and the same geographical area / section of line — e.g. 5 of 8 consecutive TCs between junctions A and B with similar site conditions; not two isolated TCs 5 miles apart.
  • A single SFI pack may be used for all failures in the same area in the same year.
  • If one TC fails in an area prone to leaf-fall WSTCF, additional TCs in that area may be tested proactively; on further failures the SFI Level 3 decides whether earlier proactive checks suffice or more testing is needed.

Retrospective RCM alarms (8-hour rule)

  • Reported less than 8 hours after occurrence: check the last 2 RCM traces; if unavailable apply Reg 3.5 for the next 2 trains.
  • Reported more than 8 hours after occurrence with continuous occupation since and 2 normal traces: classify Negligible and close.

Wheelset checks (30-minute rule)

  • Wheelset checks of the train involved must be carried out within 30 minutes of the SCWO.
  • Findings (wheelset contaminated yes/no, TCA fitted/working, sander fitted/working/used) are recorded on the WSTCF CCIL entry.