WSTCF management process
From the EM RE(S) Autumn Working Guidance 2026 v1.1 — report → FMS / MYIM → classification → response → sign-back, with the Appendix C scenarios and Appendix D sign-back levels.
Process flow
- 1 — Report receivedWSTCF reported by a signaller (train on TC showing clear) or by an RCM alarm (RADAR / Centrix). Log time, TC, line and reporting train.
- 2 — FMS fault raisedRaise the failure on FMS and record all relevant information in MYIM — a separate MYIM file per track circuit, linked together (2026 guidance §9). Record on the daily CCIL 'Autumn Suspect WSTCF' log (created 00:01 for 24h); confirmed failures transfer to the per-DU WSTCF CCIL Master Log, open all season.
- 3 — ClassifyClassify High / Low / Negligible using the hazard index (NR/L3/SIG/10047 Mod 03 §10.1) and the Appendix A flow chart (NR/L3/SIG/11231 Part 05 Module S04). RCM trace evidence drives classification — a blip under 300ms is Negligible, a sub-1 s boundary transition with the abutting TC occupied is not a WSF; no RCM at site means treat as High.
- 4 — Operational responseApply the Appendix C scenario response: Reg 3.5 / double block / TS11 as required, liaising with the Level 3 SFI so special working prevents a recurrence; arrange a wheelset check of the train involved within 30 minutes of the SCWO. Ops Managers keep the live special working register up to date.
- 5 — Treatment before attendanceWhere RCM is fitted and traces indicate railhead contamination there is no immediate requirement to send MOM / S&T to site, nor to wait for them before the railhead is treated by RHTT / MPV — but the Level 3 SFI must give permission before treatment starts. The L2/L3 SFI may still call staff to site where there is doubt or treatment is not effective.
- 6 — Sign backSign back at the Appendix D level for the classification (FF/NFF). The L2/L3 SFI can sign a TC back using RCM information exclusively and advise the Operations Manager to instruct the signaller to remove special working. L2/L3 closure needs the SFI report/statement, II RCM traces and an interlocking logger / technician's terminal extract.
- 7 — Report to NOCHigh-risk failures: Form A (first failure) / Form B (simplified, subsequent on same circuit) to the NOC by 18:00, otherwise by close of play. TS11 s15 / F3.17A form daily.
- 8 — Restore normal workingRemove special working per the restoration rules below (RHTT pass / 3 consecutive trains + good RCM traces), reinstating on red/black forecasts.
- 9 — Withdraw special workingFormal withdrawal with photographic evidence and the Withdrawal form to the NOC (see withdrawal procedure below).
Scenario guidance (Appendix C)
| Ref | Situation | Actions | Sign-back |
|---|---|---|---|
| 1.1 | Signaller reports a TC blip under a train (RCM fitted) | Ops: alert Control of a potential High-risk TC (treated as High until evidence disproves it), apply Reg 3.5 working, create the MYIM report. TSE / IIT: check the TC boundary transition and SCWO timing on RADAR & Centrix; risk is determined at this point (SMTH Part 05 Module S04). (A) Proved High or Low: inform the incident controller, ask for wheelsets to be checked (within 30 min), escalate to SFI Level 2. (B) Negligible with improved traces confirmed by TSE / IIT: Control decides when to remove the special working. | High/Low: full sign-back per the TC table, L2 or L1 (App D). Negligible: Control, after discussion with L1 (or L2 in certain scenarios), may remove the working without further escalation. |
| 1.2 | Signaller report, no RCM fitted | Treat as High risk and escalate to SFI Level 1 or 2 for interlocking checks (section 4 of the guidance). Confirm RCM is genuinely not fitted. | Full sign-back required. |
| 1.3 | Driver reports a change of aspect (COA) on an approach-release signal | As 1.1: alert Control (High until disproved), apply Reg 3.5, create MYIM. TSE / IIT check the boundary transition and SCWO timing; (A) High/Low — wheelset check within 30 min and escalate to SFI Level 2; (B) Negligible — Control decides when to remove the working. | High/Low: full sign-back per the TC table, L2 or L1. Negligible: Control with L1 (or L2) may remove the working. |
| 1.4 | RCM alarm (SCWO) — blip on a single track circuit | Follow the Appendix A flow chart / SMTH Part 05 Module S04. TSE / IIT: (A) is the trace more or less than 300 ms? (B) apply the track-section boundary clause (§14); (C) escalate to SFI Level 1 / 2 / 3 according to the hazard level. | High/Low: full sign-back per the TC table, L2 or L1. Negligible: if Reg 3.5 was implemented, remove after 2 recent good traces confirmed with L1 and/or L2. |
| 1.5 | Late-reported RCM alarm — less than 8 hours ago | TSE / IIT check the latest 2 train traces; if there has been a white period, run Reg 3.5 for the next 2 trains and confirm both traces are normal before removing. Under 8 hours: follow the Appendix A flow chart. | High/Low: full sign-back per the TC table. Negligible: remove after 2 good traces with L1 and/or L2; if Reg 3.5 was never implemented there is no sign-back requirement. |
| 1.6 | Late-reported RCM alarm — 8 or more hours ago | With continuous train occupation since and traces normal for 2 occupations, record as Negligible and close (beware differing train characteristics — a light engine may fail where heavier trains behave). If traces are not normal, treat as a live RCM failure under scenario 1.4. | Special working not implemented — nothing to remove. |
| 1.7 | Wheelset checks | A request to check wheelsets must be made within 30 minutes of the SCWO. After that there is no need — any contamination has likely been removed. | n/a |
| 1.8 | First train of the day | Covered by operational procedures (first-train arrangements), not the WSTCF flow. | n/a |
| 1.9 | Overlay AHB track circuit (section 12 list) | Reg 3.5 / special working is not required; treatment suggested at the nearest convenience. Check via a data logger (e.g. Centrix) whether the crossing entered a failed state. | No special working implemented, so no removal requirement. |
| 1.10 | Rail contamination from rust | Follow Rule Book module TS11 (GERT8000-TS11 Issue 6, Dec 2023) — failure of, or work on, signalling equipment. Appendix E rusty-rail areas: Newstead loop, Wetmore, Cricklewood, Nadins GF, Leicester P4, Uttoxeter Loop, Leicester North Jct. | n/a — TS11 arrangements |
| 1.11 | TC SCWO where already protected by special working | No change to the special working; when removal becomes desirable follow the normal procedure. Negligible-risk fault as the TC is already under Reg 3.5 — a fault must still be created and closed (vital for monitoring). | Normal removal procedure when desired. |
Sign-back levels (Appendix D)
| Failure | Fault found | No fault found |
|---|---|---|
| High — signal / interlocking / level-crossing failure | L3 | L3 |
| High — railhead contamination, unprotected | L2 | L3 |
| Low — indication-only circuit | L2 | L2 |
| Low — RCM blip under 300ms | L1 | L2 |
| Negligible — sequencing controls effective | L1 | L2 |
| Negligible — special block in force | L1 | L1 |
Where SFI Level 2 or 3 sign-back is required, closure needs (A) the SFI L2/L3 report or statement, (B) II RCM traces and (C) an extract from the interlocking loggers or technician's terminal. Sign-back at Level 2/3 may be granted on RCM evidence without site attendance. Where an event is considered NOT a wrong-side failure, the RCM traces are appended to the MYIM record (NR/SMTH Part 05 Module S04 §3.13).
Restoration of normal working
- Remove Reg 3.5 after an RHTT pass — reinstate at the end of the day.
- Remove special working after 3 consecutive trains operate the TC correctly with good RCM traces.
- Re-implement Reg 3.5 when a red or black adhesion forecast is issued.
- Where RCM is installed, removal may be considered once the contamination that caused the failure has been found and treated — RCM / Centrix evidence attached to the MYIM record and the S&TME satisfied the TCs are operating correctly.
- Sites without RCM: at the end of the leaf-fall season the S&TME (or representative) and an Ops representative jointly inspect the railhead; the whole area must be free of contamination (allowing for leaves still on trees). A MOM photo to Control supports the decision; the fault is closed in MYIM when all parties agree.
Withdrawal of special working
- Photographs of the railhead from 2–3 points plus a line-of-view shot.
- Evidence sent to the Route Control Manager and DU S&T for agreement.
- Withdrawal form submitted to the NOC.
- Change circulated via the daily record of special working (Appendix K) and the 18:00 Autumn Log.
Grouping of TC failures
- Failures may be grouped under one SFI pack when they share the same line, the same interlocking area and the same geographical area / section of line — e.g. 5 of 8 consecutive TCs between junctions A and B with similar site conditions; not two isolated TCs 5 miles apart.
- A single SFI pack may be used for all failures in the same area in the same year.
- If one TC fails in an area prone to leaf-fall WSTCF, additional TCs in that area may be tested proactively; on further failures the SFI Level 3 decides whether earlier proactive checks suffice or more testing is needed.
Retrospective RCM alarms (8-hour rule)
- Reported less than 8 hours after occurrence: check the last 2 RCM traces; if unavailable apply Reg 3.5 for the next 2 trains.
- Reported more than 8 hours after occurrence with continuous occupation since and 2 normal traces: classify Negligible and close.
Wheelset checks (30-minute rule)
- Wheelset checks of the train involved must be carried out within 30 minutes of the SCWO.
- Findings (wheelset contaminated yes/no, TCA fitted/working, sander fitted/working/used) are recorded on the WSTCF CCIL entry.